医療施設の熱源入替に伴う、フロン回収作業、冷温水配管繋ぎ替え、防熱作業、ラッキング作業を注文頂き、先日完工致しました。
![](https://nsk-setsubi.com/wp-content/uploads/img_3804.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_3809.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_3814.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_3805.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_3818.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_3827.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_3810.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4005.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4014.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4012.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4009.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4013.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4020.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4023.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4019.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4047.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4046.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4044.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4052.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4049.jpg)
![](https://nsk-setsubi.com/wp-content/uploads/img_4038.jpg)
打合せの段階から、基礎自体が小さく配管の取り回しが難しいとわかっていたのですが、協力業者の配管工さん、保温工さんが現場で考えながら綺麗に収めてくれました。保温ラッキングの工程が、検査の関係で、2日しかなくて保温工さんには無理を言って収めて頂きました。
検査関係も問題なく終わり工程通り引き渡す事が出来ました。
協力業者の皆様ありがとうございました。
投稿日:
医療施設の熱源入替に伴う、フロン回収作業、冷温水配管繋ぎ替え、防熱作業、ラッキング作業を注文頂き、先日完工致しました。
打合せの段階から、基礎自体が小さく配管の取り回しが難しいとわかっていたのですが、協力業者の配管工さん、保温工さんが現場で考えながら綺麗に収めてくれました。保温ラッキングの工程が、検査の関係で、2日しかなくて保温工さんには無理を言って収めて頂きました。
検査関係も問題なく終わり工程通り引き渡す事が出来ました。
協力業者の皆様ありがとうございました。